Date: 17 January 2018 · Location: C6 Księcia Janusza station construction site, Wola, Warsaw · Organisers: Koło Miłośników Metra, hosted by Gülermak

Front of TBM S646 Krystyna at level -2 of the C6 Księcia Janusza metro station site
Level -2 through the launch shaft: right, the front of TBM Krystyna, with the back-up gantries behind. Photos: Koło Miłośników Metra.

On 17 January 2018 the 12 m front section of tunnel boring machine S646 Krystyna lay at the bottom of the launch shaft at C6 Księcia Janusza station. 22 members of the Metro Enthusiasts’ Circle (KMM) saw it a few weeks before it started boring towards Rondo Daszyńskiego.

“Number six”: furthest west and furthest ahead

This was our third visit to stage I of the western section of line M2, built by Gülermak. We had been to C7 Młynów twice before. The section is about 3.4 km long with three stations. C6, working name Księcia Janusza, lies furthest west and was to become the terminus of line M2 on opening. That is why sidings are being built beyond it for stabling trains between peaks and overnight.

With its sidings the station is large, and the TBMs were to start from here, so it was begun first. By January 2018 the roof slab was complete, and the most interesting work had moved underground.

Construction site of metro station C6 Księcia Janusza seen from a building on Górczewska Street
The C6 site seen from a building on Górczewska Street. Photos: Koło Miłośników Metra.

The information point at 8 Płocka Street was too far away, so for once we met directly at the gate on Księcia Janusza Street at 11:30. In the site office we had a safety briefing and received helmets, hi-vis vests and safety boots.

Safety briefing before the tour of the C6 metro station site
Safety briefing in the site office. Photos: Koło Miłośników Metra.

The access opening and the mezzanine

Walking across the roof slab past workers and machines, we reached the first of the two largest access openings. Workers use it to reach the lower levels, and cranes lower materials and equipment through it. A stair tower at its edge took us down to the mezzanine at level -1, and we walked almost the full length of the station.

Stair tower in the access opening and mezzanine of metro station C6 Księcia Janusza
The stair tower in the access opening and the mezzanine seen from ground level. Photos: Koło Miłośników Metra.

The launch shaft: Krystyna in pieces

The second large opening is the launch shaft. On 5 January 2018 the 12 m front section of S646 Krystyna was lowered through it to level -2. Over the following days the back-up gantries followed in sections, 85 m long once assembled. Assembly was in full swing during our visit. The contractor planned to start the machine on 10 February and, after checks and calibration, begin boring the northern tunnel by 20 February at the latest. The tunnels were to link the section with the then terminus C9 Rondo Daszyńskiego.

A cradle and portal for Maria

Krystyna has a twin: TBM S644 Maria. On 6 December 2017 Maria finished the southern tunnel from C18 Trocka to C15 Dworzec Wileński on the eastern section built by Astaldi. It was dismantled, and on the night of 14–15 January its parts began to be moved to the western end of the line.

At level -2 a reinforced-concrete cradle was waiting for it to push off from, together with a portal, a steel ring known as a “false tunnel” that provides an extra seal where the tunnel meets the station box. Maria was to be lowered in early February and start the southern tunnel at the end of February, a few days after Krystyna.

Cradle and portal for TBM Maria at level -2 of metro station C6
Left, the front of Krystyna; right, the cradle and portal waiting for Maria. Photos: Koło Miłośników Metra.
S646 KrystynaS644 Maria
Previous jobnot stated in the reportsouthern tunnel C18 Trocka – C15 Dworzec Wileński (to 6 Dec 2017)
Lowered into shaft5 Jan 2018 (front section)planned for early February 2018
Start of boringby 20 Feb 2018 (northern tunnel)planned end of February 2018 (southern tunnel)
Lengthfront 12 m, 85 m with back-uptwin design

We returned to the surface by the same stairs, took a group photo and handed back our protective gear. We thank Gülermak for our third meeting on the Wola metro site.

Group photo of the Metro Enthusiasts’ Circle on the C6 Księcia Janusza site
Group photo on the site. Photos: Koło Miłośników Metra.

At a glance

Date17 January 2018
SiteC6 Księcia Janusza station, stage I of the western section of line M2 (approx. 3.4 km, 3 stations)
ContractorGülermak
Participants22
TBMsS646 Krystyna, S644 Maria

Frequently asked questions

When did TBM Krystyna start boring in Wola?

According to the contractor’s plan in January 2018, S646 Krystyna was to be started on 10 February and begin the northern tunnel by 20 February 2018 at the latest.

Where did TBM Maria come from?

From the eastern section of line M2, where on 6 December 2017 it completed the southern tunnel between C18 Trocka and C15 Dworzec Wileński.

Why were sidings built beyond station C6?

C6 was to be the terminus of line M2, and the sidings are used to stable trains between peaks and overnight.

What is the portal at a TBM launch shaft?

A steel ring, the so-called false tunnel, that provides an additional seal where the tunnel joins the station box.

Trip report originally published on the website of the Metro Enthusiasts’ Circle (Koło Miłośników Metra) (19 January 2018). Text rewritten and translated by the Zrobotyzowani editorial team. Original Polish report on kmmetra.pl. Photos: Koło Miłośników Metra.