Date: 21 December 2017 · Location: C7 Młynów station construction site, Wola, Warsaw · Organisers: Koło Miłośników Metra, hosted by Gülermak

On 21 December 2017, exactly five months after our first visit, we returned to the construction site of C7 Młynów station. 24 people came, the largest turnout in the Circle’s history of tours so far. This time we did not stand at the edge of the excavation but went beneath the finished roof slab.
From the information point to the site office
As in July, we met at the project information point on Płocka Street. After 13:00 the group, in helmets, hi-vis vests and safety boots, set off onto the site. In the container office the site manager gave a short history of the station, followed by a safety briefing.


Progress in December 2017
| Element | Status on 21 December 2017 |
|---|---|
| Diaphragm walls | all complete, 31 m deep |
| Roof slab | complete, with expansion joints |
| Excavation of level -1 | under way, completion planned for December 2017 |
| Level -1 slabs | under way, completion planned for end of January 2018 |
| Excavation to platform level | started a few days earlier on the eastern side |
Excavators, concrete mixers and cranes were at work on the surface. The station was built using the top-down method: walls and roof slab first, then soil removed from underneath.

Down the stair tower to level -1
Roughly halfway along the site stood a temporary stair tower. We used it to go beneath the roof slab onto a concreted section of the mezzanine at level -1. West of the stairs, reinforcement alternated with finished concrete, as the slabs of this level were still being cast.


On the other side, work had already started going deeper. An opening had been left in the level -1 slab, and an excavator in it was removing soil from where the platform will be.
We returned to the surface by the same stairs and took a group photo by the site gate. We thank Gülermak for another close look at the works. It was the Circle’s last meeting of 2017.

At a glance
| Date | 21 December 2017 |
| Site | C7 Młynów station, line M2 |
| Contractor | Gülermak |
| Participants | 24 (record turnout in 2017) |
| Diaphragm wall depth | 31 m |
Frequently asked questions
How deep are the diaphragm walls of Młynów station?
According to the site team in December 2017, the diaphragm walls of C7 Młynów reach 31 m.
How was Młynów station built?
Using the top-down method: diaphragm walls and roof slab first, then each level excavated beneath the slab down to the platform.
How is soil removed from under the slab?
Through openings left in the slabs. At Młynów an excavator worked inside an opening in the level -1 slab.
Trip report originally published on the website of the Metro Enthusiasts’ Circle (Koło Miłośników Metra) (27 December 2017). Text rewritten and translated by the Zrobotyzowani editorial team. Original Polish report on kmmetra.pl. Photos: Koło Miłośników Metra.