Date: 21 December 2017 · Location: C7 Młynów station construction site, Wola, Warsaw · Organisers: Koło Miłośników Metra, hosted by Gülermak

Excavator digging towards platform level through an opening in the level -1 slab at Młynów metro station
Eastern part of level -1: digging down to platform level. Photos: Koło Miłośników Metra.

On 21 December 2017, exactly five months after our first visit, we returned to the construction site of C7 Młynów station. 24 people came, the largest turnout in the Circle’s history of tours so far. This time we did not stand at the edge of the excavation but went beneath the finished roof slab.

From the information point to the site office

As in July, we met at the project information point on Płocka Street. After 13:00 the group, in helmets, hi-vis vests and safety boots, set off onto the site. In the container office the site manager gave a short history of the station, followed by a safety briefing.

KMM tour participants at the information point and site office of Młynów metro station (1)
KMM tour participants at the information point and site office of Młynów metro station (2)
At the information point and during the presentation in the site office. Photos: Koło Miłośników Metra.

Progress in December 2017

ElementStatus on 21 December 2017
Diaphragm wallsall complete, 31 m deep
Roof slabcomplete, with expansion joints
Excavation of level -1under way, completion planned for December 2017
Level -1 slabsunder way, completion planned for end of January 2018
Excavation to platform levelstarted a few days earlier on the eastern side

Excavators, concrete mixers and cranes were at work on the surface. The station was built using the top-down method: walls and roof slab first, then soil removed from underneath.

Heavy plant on the roof slab of the C7 Młynów metro station site
Heavy plant on the site. Photos: Koło Miłośników Metra.

Down the stair tower to level -1

Roughly halfway along the site stood a temporary stair tower. We used it to go beneath the roof slab onto a concreted section of the mezzanine at level -1. West of the stairs, reinforcement alternated with finished concrete, as the slabs of this level were still being cast.

Stair tower and mezzanine concreting at level -1 of Młynów metro station (1)
Stair tower and mezzanine concreting at level -1 of Młynów metro station (2)
The stair tower seen from the mezzanine, and the western part of level -1. Photos: Koło Miłośników Metra.

On the other side, work had already started going deeper. An opening had been left in the level -1 slab, and an excavator in it was removing soil from where the platform will be.

We returned to the surface by the same stairs and took a group photo by the site gate. We thank Gülermak for another close look at the works. It was the Circle’s last meeting of 2017.

Group photo at the gate of the C7 Młynów metro station construction site
Group photo at the site gate. Photos: Koło Miłośników Metra.

At a glance

Date21 December 2017
SiteC7 Młynów station, line M2
ContractorGülermak
Participants24 (record turnout in 2017)
Diaphragm wall depth31 m

Frequently asked questions

How deep are the diaphragm walls of Młynów station?

According to the site team in December 2017, the diaphragm walls of C7 Młynów reach 31 m.

How was Młynów station built?

Using the top-down method: diaphragm walls and roof slab first, then each level excavated beneath the slab down to the platform.

How is soil removed from under the slab?

Through openings left in the slabs. At Młynów an excavator worked inside an opening in the level -1 slab.

Trip report originally published on the website of the Metro Enthusiasts’ Circle (Koło Miłośników Metra) (27 December 2017). Text rewritten and translated by the Zrobotyzowani editorial team. Original Polish report on kmmetra.pl. Photos: Koło Miłośników Metra.

Privacy Preference Center