Date: 4 June 2019 · Location: C18 Trocka metro station and sidings, Pratulińska Street, Targówek, Warsaw · Organisers: Koło Miłośników Metra, hosted by Metro Warszawskie and Astaldi

For a few weeks it was the easternmost point of the Warsaw Metro, and no passengers had reached it yet. On 4 June 2019 nearly ten members of the Metro Enthusiasts’ Circle (KMM) saw the finished station C18 Trocka and walked along its sidings, where trains would soon reverse, wait between peaks and undergo inspections.
A terminus on Pratulińska Street
C18 Trocka was built from 11 March 2016 to 10 May 2019 as the terminus of stage I of the eastern-northern section of line M2. It lies in Targówek, along Pratulińska Street, south of the junction with Trocka Street, among multi-storey housing blocks. The canopies of its four entrances, each with a lift, echo the stairwell entrances of the nearby buildings. North of the junction lie the sidings, at the time the largest in the Warsaw Metro in several respects.
Shortly before 11:00 we were welcomed by representatives of Metro Warszawskie and Astaldi, the station contractor. After a short briefing, in high-visibility vests, we entered through entrance no. 2 on the north-eastern corner of the junction. It soon became clear that the route would differ from the open day held in May.
Mezzanine: customer service point, ticket machines and a one-way mirror
On level -1 we passed the furnished WTP Passenger Service Point and, beyond it, ticket machines meeting the latest guidelines, already in WTP’s new red and grey livery. The ticket gates were out of use that day, so we entered the paid area through the emergency doors.

Astaldi’s spokesperson pointed out the signs with the station name and maps. For the first time the designer, ILF Consulting Engineers Polska, mounted them on the mezzanine walls instead of free-standing on the floor; on platforms this had been done before. The walls are faced with concrete panels with distinctive grooves. Through a one-way mirror next to the stairs we could look into room 110, the station control room, fully equipped for the station supervisor.

An empty platform before opening
We went down the stairs to the northern end of the platform. For most of us it was the first sight of the finished hall, and being completely alone there made it even more striking. A single row of columns in the middle, a white and grey finish and ceiling lighting make the space bright and spacious. Add metal benches, concrete tactile paths, floor lights and the white illuminated signs familiar from the seven stations of the central section of line M2.

Seven tracks beyond the station
At the glazed doors at the end of the platform we got good news: there was no test running that day and the third rail was switched off, so we could go onto the sidings. The door on the track 1 side was opened with an access card. Along the service platform, past the main pump room, we reached the steps down to track level. Following the fence of a storage area the metro can use as it sees fit, we came to the point where two running tracks become four sidings.

The standard layout consists of two running tracks and two tracks between them, one branching off each, linked by a scissors crossover. Beyond Trocka two more sidings were added on one side and a service track on the other. In total there are 7 tracks and 7 train berths.
| Track | Role |
|---|---|
| 1 | running track in the direction of line chainage |
| 2 | running track in the opposite direction |
| 3 | inner siding, branching off track 1 |
| 4 | inner siding, branching off track 2 |
| 6 and 8 | outer sidings beyond track 2 |
| 5 | service (inspection) track on the far side of track 1 |
Tracks branching off an odd-numbered track get further odd numbers, those off an even track even numbers. The whole layout is protected by buffer stops and one-, two- and three-aspect signals. A signal’s name consists of the two-letter station code (Ta), the track number and the signal’s sequence number on that track counted from zero, e.g. Ta53. This layout was to apply until the line was extended to C21 in Bródno: the running tracks would then become through tracks, leaving five berths. Track 5 was also planned to be connected back to track 1 beyond the service room.

Chamber T966 with an inspection pit
From track 1 we turned off along track 5, passed signal Ta53 and a gentle curve, and entered room T966 through a roller door. This service chamber is about 150 m long and 7 m wide. The track here has an inspection pit nearly 1.5 m deep, with steps down every 20 m, and an overhead conductor rail instead of a third rail beside the track, so that people working in the pit and around the train are not at risk of electric shock. At the end stand a single-aspect signal Ta54 and a temporary buffer stop.
At the end of the conductor rail, mobile trolleys with guide cables and flexible power leads were parked. Their connectors plug into pins next to the current collectors on the bogies of the train being serviced. The supply is enough to power the train’s equipment and to move it slowly along the inspection track.

“The end of the metro”
Through a door on the far side of the inspection track we came out at a spot someone dubbed “the end of the metro”. There was some truth in it: it was the easternmost point of the Warsaw underground until the section to C21 opened. The end diaphragm wall is prepared to receive, a few years later, the TBMs boring the tunnels from Bródno, and the trackbed was built so the extension can be connected easily. We walked across the tracks: on one side a row of buffer stops, signals and technical rooms, on the other the sidings with service platforms between them, and countless services along the walls.

An announcement in a station without passengers
By the inspection track our guides took a group photo of us in front of the buffer stop. We walked back along the service chamber and track 1, then via the service platform to the passenger platform. At its southern end we looked into the tunnels towards C17 Targówek Mieszkaniowy. Astaldi’s spokesperson answered our many questions throughout.
As we headed for the exit, an announcement about the yellow emergency telephones came over the speakers. It raised smiles, since the station was not yet in service. Not in service, but ready: the new section was already linked to all the systems of the central section of line M2, including the voice alarm system.

We left through entrance no. 2 from the site still in the contractor’s hands. We thank Metro Warszawskie and Astaldi for the visit during the acceptance process, especially for extending the route to the sidings, and our guides for the group photo.
At a glance
| Date | 4 June 2019 |
| Site | station C18 Trocka and sidings, terminus of stage I of the eastern-northern section of line M2 |
| Station construction | 11.03.2016 – 10.05.2019 |
| Hosts | Metro Warszawskie, Astaldi (contractor) |
| Designer | ILF Consulting Engineers Polska |
| Participants | nearly 10 |
| Sidings | 7 tracks, 7 train berths (5 after the extension to C21) |
| Chamber T966 | approx. 150 × 7 m, inspection pit approx. 1.5 m, overhead conductor rail |
Frequently asked questions
How many sidings are there beyond Trocka metro station?
Seven: two running tracks, sidings 3, 4, 6 and 8 and service track 5. In June 2019 this gave 7 train berths; after the extension to C21 there were to be 5.
What is room T966 beyond Trocka used for?
It is a service chamber with inspection track 5, an inspection pit nearly 1.5 m deep and an overhead conductor rail, where trains can be inspected and repaired.
How are signals on Warsaw Metro sidings named?
The name combines the two-letter station code (Ta for Trocka), the track number and the signal’s sequence number on that track counted from zero, e.g. Ta53 and Ta54 on track 5.
Why was the wall at the end of the tracks beyond Trocka called “the end of the metro”?
It was the easternmost point of the metro in Warsaw. The diaphragm wall is prepared to receive the TBMs boring the tunnels from Bródno.
Trip report originally published on the website of the Metro Enthusiasts’ Circle (Koło Miłośników Metra) (7 June 2019). Text rewritten and translated by the Zrobotyzowani editorial team. Original Polish report on kmmetra.pl. Photos: Koło Miłośników Metra.