Date: 5 March 2019 · Location: C16 Szwedzka station construction site, Strzelecka Street, Praga-Północ, Warsaw · Organisers: Koło Miłośników Metra, hosted by Astaldi

Platform hall of Warsaw Metro station C16 Szwedzka with perforated-metal ceiling before opening
The C16 platform hall in March 2019. Photos: Koło Miłośników Metra.

Passengers were to hear the announcement “Next station: Szwedzka” a few months later. On 5 March 2019 fewer than ten members of the Metro Enthusiasts’ Circle (KMM) saw station C16 Szwedzka in its final phase of construction and walked into the tunnel towards Dworzec Wileński.

The smallest of three, but wide

C16 Szwedzka is the smallest station of stage I of the eastern-northern section of line M2, built by Astaldi, and the last in Praga-Północ before Targówek. It lies along Strzelecka Street, east of the junction with Szwedzka Street. It is short but wide, because the technical rooms were placed alongside rather than at the ends.

ParameterValue
Volume62,674 m³
Length135.3 m
Max. width50.89 m
Entrances and lifts4 entrances, 3 lifts
Top of railapprox. 14.50–15.50 m below ground

At 10:00 we met at the site entrance on Szwedzka Street. After a safety briefing we went underground through the nearest entrance, W1, as Strzelecka Street was being resurfaced on the north side.

Entrance W1 of metro station C16 Szwedzka on the south-western side
Entrance W1 on the south-western side of the station. Photos: Koło Miłośników Metra.

Clinker brick like Praga’s tenements

Fit-out was under way on the western mezzanine. The ceilings and the glazing of the ticket hall and retail units were in place. Some walls were faced with clinker brick, a nod to the brick tenements of Praga around the station.

Clinker brick on the western ticket-hall wall of Szwedzka metro station
Clinker brick on the western ticket-hall wall. Photos: Koło Miłośników Metra.

An almost finished platform

Most of the platform was paved with stone slabs, including tactile warning strips. The ceiling and track-side walls are clad in white and dark grey perforated metal, and the walls by the stairs and at the platform ends in grey stone. Lighting, some cameras, smoke detectors and name signs were installed. Some signs, monitors and benches were still to come.

A door in the side wall of the platform stairs led to the under-platform level. It houses fire-protection and voice-alarm equipment, passenger-information systems, escalator and lift machinery, sanitary installations and station pumps. There was so much space that someone joked about a gym or a wedding hall.

Technical equipment in the under-platform level of metro station C16 Szwedzka
Under-platform equipment. Photos: Koło Miłośników Metra.

100 metres along tunnel D16

Track and line-wide systems were complete. The first round of test running had taken place from late January to late February. In the break before the second round, with the third rail switched off, we went down the steps at the end of the platform into the northern tunnel D16 towards C15 Dworzec Wileński. After about 100 m we stopped at signals Sz20 and Sz21. Beyond, the tunnel curved gently right, then left again before the sidings beyond C15.

Tour participants in metro tunnel D16 with station C16 Szwedzka in the distance
In tunnel D16, with station C16 in the distance. Photos: Koło Miłośników Metra.

Someone dubbed the small platform next to the tunnel portal the “goods platform”. During construction materials were indeed stored there, but it is a service platform leading to the side technical rooms. Behind the southern track-side wall are a switchroom, pump room, staff rooms and two reserve rooms for the metro’s future needs.

At about 11:00 we returned to the surface. We thank Astaldi for the visit and our guides for taking the group photo.

Strzelecka 46 tenement, remains of the Pollena factory and the ventilation intake of Szwedzka metro station
Strzelecka 46, remains of the Pollena factory and the station ventilation intake, with entrance W2 behind. Photos: Koło Miłośników Metra.

At a glance

Date5 March 2019
Sitestation C16 Szwedzka, stage I of the eastern-northern section of line M2
ContractorAstaldi
Participantsfewer than 10
Test runningfirst round: late January – late February 2019
Tunnel D16walk of about 100 m to signals Sz20 and Sz21

Frequently asked questions

Why is Szwedzka station so wide?

The technical rooms are located alongside the station rather than at its ends. The station is 135.3 m long and up to 50.89 m wide.

Why is there clinker brick on the walls at Szwedzka?

It refers to the brick tenements of Praga around the station.

How deep are the tracks at Szwedzka station?

The top of rail is about 14.50–15.50 m below ground level.

When did test running start on the section with Szwedzka?

The first round ran from late January to late February 2019.

Trip report originally published on the website of the Metro Enthusiasts’ Circle (Koło Miłośników Metra) (7 March 2019). Text rewritten and translated by the Zrobotyzowani editorial team. Original Polish report on kmmetra.pl. Photos: Koło Miłośników Metra.