Date: 22 February 2019 · Location: C7 Młynów station construction site, Wola, Warsaw · Organisers: Koło Miłośników Metra, hosted by Gülermak

In April 2018 a TBM stood at C7 Młynów. On 22 February 2019, in the same place, track bed was being concreted and rails laid. Nearly 20 members of the Metro Enthusiasts’ Circle (KMM) saw the station less than nine months before the planned completion.
Through entrance W4 to the mezzanine
As usual we started at the information point on Płocka Street: paperwork, safety briefing, boots, vests and helmets. We entered the station from the east and went down the bare concrete stairs of entrance W4 to the mezzanine.

Useful destruction
In the future ticket hall we came upon an unusual job: demolishing part of the finished structure. There is only one way to connect an entrance to the station box, by cutting through a section of the diaphragm wall. On the north-eastern side, entrance W3 was being joined in this way, using a remote-controlled hydraulic breaker, a small loader and a few workers.

Then we looked into the technical rooms, where construction was being finished, and took the fixed stairs down to the platform.

Platform and tracks where the TBM stood
The platform slab carried the first sample floor tiles; the ceiling had acoustic panels and cable trays, and similar structures ran along the track-side walls. At the lowest level, where the TBM had stood ten months earlier, there was reinforcement and blocks, track bed was being concreted and rails installed. The same work was going on in the tunnels next to the station.
Entrance W1 and Warszawa Młynów station
On the western mezzanine the wall had already been opened to entrance W1, the most important one for interchange. It is closest to the platforms of the railway stop on the Warsaw ring line. During the modernisation of railway line 20, PKP Polskie Linie Kolejowe renamed that stop from Warszawa Koło to Warszawa Młynów to match the working name of the metro station, long before the metro opened.

Level -1.5
Finally, as promised, we visited the western back-of-house area. Some technical rooms here sit between the mezzanine and the platform hall, at level -1.5. Contractor staff took our group photo on the platform, and we returned to the surface via entrance W4.

We thank Gülermak for showing us the works at this stage and for the group photo.
At a glance
| Date | 22 February 2019 |
| Site | C7 Młynów station, line M2 |
| Contractor | Gülermak |
| Participants | nearly 20 |
| Interchange | Warszawa Młynów railway stop (formerly Warszawa Koło), line 20 |
Frequently asked questions
How is an entrance connected to a metro station box?
By cutting through a section of the finished diaphragm wall. At Młynów this was done with a remote-controlled hydraulic breaker.
Why was Warszawa Koło railway stop renamed Warszawa Młynów?
PKP PLK renamed it during the modernisation of line 20 to match the name of the C7 Młynów metro station being built next to it.
What is level -1.5 at Młynów station?
Technical rooms located between the mezzanine and the platform hall in the western part of the station.
Trip report originally published on the website of the Metro Enthusiasts’ Circle (Koło Miłośników Metra) (25 February 2019). Text rewritten and translated by the Zrobotyzowani editorial team. Original Polish report on kmmetra.pl. Photos: Koło Miłośników Metra.