Date: 20 November 2019 · Location: C4 Bemowo metro station and sidings construction site, Górczewska / Powstańców Śląskich Streets, Bemowo, Warsaw · Organisers: Koło Miłośników Metra, hosted by Gülermak

A year after the contract was signed, the metro was starting to show in Bemowo. On 20 November 2019 the Metro Enthusiasts’ Circle (KMM) visited the construction of station C4 by the district town hall and of the sidings beyond it. Both were to be unusual in several respects, so we wanted to follow them from the very start.
Powstańców Śląskich or Bemowo
The contractor’s working name for the station was Powstańców Śląskich, while the latest proposal from the Warsaw City Council’s street-naming committee was simply Bemowo. Both make sense: the station lies under Górczewska Street at its junction with Powstańców Śląskich Street, next to the Bemowo District Office. Together with station C5 Ulrychów in Wola it forms the shortest part of line M2, just two kilometres long: stage II of the western section.
| Stage | Date |
|---|---|
| Contract with Gülermak | November 2018 |
| Building / detailed design | Metroprojekt / ILF |
| Preparations, utility diversions | first months after signing |
| Sidings diaphragm walls | from August 2019 |
| Station entrance walls | from October 2019 |
| Planned completion | November 2021 |
Two separate structures with a TBM in between
At 11:30 we met at the information point on Kossutha Street. After the formalities and a safety briefing, wearing protective gear, we went onto the neighbouring sidings site before 12:00. From the site offices we watched a grab rig at work and listened to our guide.

Station C4 and its sidings will in practice be two separate structures, the second such case in Warsaw after A11 Politechnika. The TBM will be lowered into a launch shaft at the eastern end of the sidings, bore about 150 m of tunnel to the station’s western wall, be pulled through the station and continue to C5 by the Wola Park shopping centre.
The sidings themselves will be unusual too. Besides the standard four tracks, two running tracks and two stabling tracks between them, two technical tracks will be built to the south: one for washing and cleaning trains, the other with an inspection pit.
Nine entrances
The station will have 9 entrances. Four lead straight to the two mezzanines. The other five are linked to the western part of the station by corridors under the junction: two entrances on the western corners and three leading directly to the tram platforms. At the design stage pipe jacking was considered for these passages to reduce disruption on the surface. In the end the standard cut-and-cover method with diaphragm walls was chosen, and the corridors will finally be connected by breaking through the station box, as at the entrances of C17 Targówek Mieszkaniowy and C7 Młynów.

We went on to discuss the works and plans for the future development of the metro in Warsaw. Some climbed to the upper floor of the site office for photos from above. Around 12:30 we returned the helmets, vests and boots and, at the guide’s suggestion, continued the conversation on a walk around the site.
Camera, shrine or benchmark?
On Powstańców Śląskich Street we passed a visualisation of the platform hall on the site fence and, from the other side of Górczewska Street, saw how large the sidings structure is. From the Bemowo-Ratusz bus stop towards the city centre we could see a concrete column with a benchmark by St Luke the Evangelist church. It is part of the geodetic monitoring system that measures height differences between points on the ground. Our guide said some visitors to the information point had taken it for a camera, or even a wayside shrine.
The last stop was the pavement between the site fence and the district office. Through gaps in the fence we watched the second grab and the bentonite plant at work. The meeting ended at 13:00.

We thank Gülermak, the main contractor for all the metro stations then under construction in Warsaw, for the chance to follow progress on another section of line M2 up close.
At a glance
| Date | 20 November 2019, 11:30–13:00 |
| Site | station C4 Bemowo (working name Powstańców Śląskich) and sidings, stage II of the western section of line M2 |
| Contractor | Gülermak |
| Design | building: Metroprojekt, detailed: ILF |
| Sidings | 4 standard tracks + 2 technical tracks (washing, inspection pit) |
| Entrances | 9, including 3 to tram platforms |
| TBM | launch at the eastern end of the sidings, approx. 150 m to the station |
Frequently asked questions
Why are Bemowo metro station and its sidings separate structures?
A TBM bores about 150 m of tunnel between them: it starts from a shaft at the eastern end of the sidings, reaches the station’s western wall and is pulled through towards C5. It is the second such case in Warsaw after A11 Politechnika.
What will the technical tracks beyond Bemowo station be used for?
Two extra tracks south of the standard four: one for washing and cleaning trains, the other with an inspection pit.
How many entrances does Bemowo metro station have?
Nine. Four lead directly to the mezzanines and five are connected by corridors under the junction, three of them straight to the tram platforms.
What is the concrete column on Górczewska Street by St Luke’s church?
A benchmark, part of the construction’s geodetic monitoring, used to measure height differences between points on the ground.
Trip report originally published on the website of the Metro Enthusiasts’ Circle (Koło Miłośników Metra) (25 November 2019). Text rewritten and translated by the Zrobotyzowani editorial team. Original Polish report on kmmetra.pl. Photos: Koło Miłośników Metra.